Projects

Local Windfarm Projects

The following table provides an overview of the local windfarm projects which ProWA has actively supported or is currently supporting, listed in chronological order based on decision date.

Project Developer District Grid ref Status  Comments
           
Swinford Nuon Renewables Harborough
(Leics)
SP572815
Approved
Dec 2009 following public inquiry.
Read the Secretary of State decision document
.
Swinford Windfarm is now operational.
See pertinent blog post here.
           
New Albion
Infinergy Kettering
(Northants)
SP846843 Approved
Jan
2010 at Kettering Borough Council planning meeting.
Read the committee report and the approval
document
.
Listen to interviews
with the chair of the planning committee for Kettering
Borough Council and the Chief Executive of Infinergy.
           
Low Spinney Broadview Harborough
(Leics)
SP559892 Approved
March
2010 following public inquiry.
Low Spinney Windfarm is now operational.

           
Palmers Hollow Ridgewind Melton
(Leics)
SK820400 Dismissed
July 2010 following public inquiry.
Read the appeal
decision.
ProWA is disappointed by the
inspector’s decision.
           
Yelvertoft Your Energy Daventry
(Northants)
SP579758 Approved
July 2010
following public inquiry.
Read the appeal
decision.
The Inspector took note of the close proximity of the M1 motorway and A14 trunk road, and disagreed with the
analysis of sound given by a representative of the objectors. Much of the report relates to visual impact of the turbines as relating to Stanford Hall; the
Inspector was of the opinion such impacts were slight and
not harmful.
Yelvertoft Windfarm is now operational.
           
Harrington Nuon Renewables Daventry
(Northants)
SP767782
Dismissed
Sept 2010 following public inquiry.
Read the appeal
decision.
The appeal decision is a disgrace. Click here
to read why.
           
Dalby
Ecotricity Melton
(Leics)
SK652238
Approved
Dec 2010 at Melton Borough Council planning meeting.
Read the decision
notice.
           
Wanlip

Severn Trent

Charnwood
(Leics)
 
SK592119
Approved
March 2011 following appeal.
Read the appeal
decision.
The Wanlip turbine is now operational.
See pertinent blog post here.
           
Kelmarsh
E.ON Daventry (Northants) SP723784 Approved Dec. 2011 following
appeal.
           
Winwick
E.ON Daventry (Northants) SP636744 Approved July 2012 following
appeal.
           
Watford Lodge Volkswind Daventry (Northants) Awaiting decision.
           
Boddington Reservoir Partnerships for Renewables Daventry
(Northants)
SP496542 Approved. The Boddington turbine is now operational.
See pertinent blog post here.
           
Starbold Broadview Stratford-on-Avon (Warwcks) SP384551 Awaiting application.
Spring Farm
Ridge
Broadview South Northants SP570430 Awaiting decision.
           
Gartree Energy4All Harborough
(Leics)
Withdrawn For background information see
https://sites.google.com/site/jonnyinlubenham
           
M1 Windfarm Wind Prospect
Developments
South Northants SP778520 Approved Dec 2012 at South Northants Council planning meeting.
           
Bransford Bridge
SSE Churchover
(Warks)
  Awaiting decision.  
Burton
Wold South
Infinergy Kettering
(Northants)
  Approved March 2012 at Kettering
Borough Council planning meeting.
Read the committee
report.
 
           
Steadfold Lane
REG Windpower
Ketton
(Rutland)
  Withdrawn.  
M1J18
Turbines
Airvolution Daventry
(Northants)
  Approved May 2012 at Daventry District Council planning meeting
       

Last partial update 11/2019
(further update required)

Share this page: